Questions the Valley Range application leaves open before Dec. 10

The packet Montezuma County posted for the Dec. 10 planning hearing leaves the battery equipment, the firefighting water supply and the cleanup bond to be settled after a permit. Its draft emergency plan describes a different place. Here is what the planning commission and the public can ask.

Map of the proposed Valley Range Energy Park east of Cortez: three fenced solar panel areas south of U.S. 160, a battery storage and substation yard at the west end, and the site entrance off U.S. 160, about 2 miles west of the Mesa Verde National Park entrance
Map: Cortez Current; © OpenStreetMapThe proposed solar panel areas, security fences, battery storage and substation yard and site entrance, placed using the developer's Nov. 19 site plan and the coordinates in its glare study.

The Montezuma County Planning and Zoning Commission holds its public hearing on the Valley Range Energy Park on Thursday, Dec. 10, at 6 p.m. in the commissioners’ hearing room at 109 W. Main St. in Cortez. Written comments must be filed by Dec. 3 to reach the commission’s review materials.

The county has now posted the application. The notice packet runs 69 pages, and 30 more attachments sit beside it on the county’s online permit portal, including a 28-page draft emergency response plan. The Cortez Current read the packet, the draft plan and the other 29 attachments. Links to every file are at the end of this story.

Many of the decisions neighbors have asked about haven’t been made. The developer, Accelergen Energy, says it has not bought the major equipment and wants to keep its choice of vendors and design open until it applies for building permits. The fire water tank’s size, the emergency phone numbers and the cleanup bond’s dollar amount are all left for later. Some of the packet’s own figures don’t agree with one another.

The Cortez Current emailed questions about these findings to Accelergen on Nov. 27. On Oct. 22, the company’s public relations firm, Bantam Communications, wrote that it would be “happy to answer your questions” about the battery site, setbacks, emergency plan and new ownership, and expected to have answers by noon the next day. None came, and neither the company nor Bantam replied to the Current’s later emails on Oct. 23 and Nov. 11. Automatic replies to the Nov. 27 email said Bantam’s office reopens Nov. 30 after the Thanksgiving holiday. The Current will report any response.

The commission doesn’t make the decision. It recommends approval or denial to the Board of County Commissioners, and the application form itself says the commissioners may impose “conditions and safeguards” (p. 2). The questions below are ones the commission, or anyone filing a comment, could put to the developer and county staff before that recommendation. Page numbers refer to the county’s notice packet unless the emergency plan is named.

The emergency plan describes a different site

The draft emergency response plan, Attachment 18, calls itself a “preliminary draft” written as a starting point for talks with the Cortez Fire Protection District. Much of it is a fill-in template, with blanks such as “[Date],” “[TBD]” and “[Insert Project Name].”

Its description of the facility doesn’t match Valley Range. On page 6, the plan says the property is bordered by Calumet Road, Railroad Lane and the Atchison, Topeka and Santa Fe Railway, is crossed by two natural gas pipelines and holds about five oil and gas wells “according to the New Mexico Oil Conservation Division.” It calls the vegetation typical of the Chihuahuan Desert. On page 7, it says the project substation connects to Southwestern Public Service Company’s 230-kilovolt system. The application says Valley Range would connect to Tri-State’s 115-kilovolt East Cortez substation (p. 28).

The plan’s emergency contact page is blank except for three phone numbers, all with New Mexico’s 505 area code (plan, p. 5). It says the contacts will be filled in with the building permit submittal.

Questions to ask:

  • Was this plan written for Valley Range? When will the county and the fire district get a version that describes this site?

  • Will the commission see a site-specific emergency plan before it votes, or only after a permit is granted?

  • Has the Cortez Fire Protection District reviewed the draft, and does it support it? County standard 17 says a “letter of adequacy” from law enforcement or emergency services “may be required” (p. 4). Will the county require one before the commissioners’ hearing?

Fire water, detection and warning the neighbors

The plan says a water tank and pump beside the battery yard would be the fire protection supply. The tank’s size, flow and run time are all “[TBD],” to be “finalized with the local Fire Marshal” (plan, p. 6). The nearest fire hydrant is “[insert location]” (plan, p. 20). Whether the battery enclosures have automatic fire detection is written as “[are/are NOT]” (plan, p. 19).

For a battery fire with nothing nearby at risk, the plan says “letting the enclosure burn may be the best and safest approach” (plan, p. 14). It tells responders to stage at least 300 feet away, a distance it says will be set with the battery maker (plan, pp. 12-15). It warns that failing batteries can give off a toxic gas mixture that can include hydrogen fluoride and carbon monoxide, and that the gas is more likely when the batteries don’t catch fire (plan, p. 17).

The plan tells responders to sample gas at the fence line and consider shelter-in-place or evacuation orders for the surrounding area (plan, pp. 14-15). But it says it does not include evacuation procedures for anyone outside the project property (plan, p. 8). It refers to a “Plume Analysis prepared for the Project” (plan, p. 17); no plume analysis is among the posted attachments. Who would test the air, water and soil after a fire is “TBD” (plan, p. 22).

Questions to ask:

  • How large will the fire water tank be, and how long must it supply water? Should those numbers be set as permit conditions now rather than after approval?

  • Will the battery enclosures have automatic fire detection and gas detection?

  • Who would order shelter-in-place or evacuation for neighbors on Road H, Road 29.4 Loop and the campground south of the site, and how would they be warned?

  • Has a plume analysis been done? If so, will the county post it? The developer also says its fire protection engineer is preparing a Hazard Mitigation Analysis (Attachment 4). Is it finished?

  • Who pays for air, water and soil testing after a fire?

  • Commissioner-elect Rodney Cox said in October that mutual-aid agreements with surrounding fire districts were not in place. Are they now?

What equipment, and could it change?

The preliminary site plan names Tesla Megapack 3 XL battery units with lithium iron phosphate cells, Qcells solar modules and Nextracker trackers (pp. 29-30). But the application also says the major equipment “has not been procured” and that the developer “seeks to preserve vendor selection and design flexibility” (p. 29). A footnote in the emergency plan goes further: the battery chemistry “has not been finalized” (plan, p. 16). The contractors who would design and build the project haven’t been chosen (p. 31).

The application says the batteries should last about 20 years and the panels about 35, and that neither is planned to be replaced (p. 24). The site plan’s battery table lists 144 Tesla Megapack 3XL units at the start, 36 blocks of four, holding 663.6 megawatt-hours. That is about 2.7 times the 250 megawatt-hours the project would deliver to the grid (p. 57). A note adds that the site “will have 3 year over build with augmentation with 77 containers.” The cleanup estimate counts the 144 units (Attachment 5) but none added later.

Questions to ask:

  • Would a permit tie the developer to lithium iron phosphate batteries and the layout shown? What changes would send the project back to the county for a new hearing?

  • How many battery containers would be installed at first, and how many after “augmentation”? Does the battery yard grow over time?

  • What happens to the battery system after 20 years, when the project is meant to run for 35?

Noise: two studies, two answers

On page 19, the application says modeling puts the loudest point on the project boundary at about 54 decibels, north of the battery yard, and the nearest homeowner’s property line at just over 50 decibels at night. On page 45, it cites a February 2025 noise study with boundary levels of about 37 to 51 decibels. It also offers a limit: the plant would not put more than 50 decibels on a neighboring house that exists when the permit takes effect. The county’s standard is 55 decibels at night on a boundary next to homes (p. 4). The sound study will be redone with the final equipment before building permits, the application says (p. 19). The noise model actually attached (Attachment 17) predicts no more than 47 decibels at 188 nearby homes, but it was run on an Aug. 21 layout, gives no property-line figures and does not list the equipment modeled.

Questions to ask:

  • Which study is current, and what equipment did it model?

  • Will the 50-decibel limit at neighboring homes be a permit condition? Who measures it, and what happens if it’s exceeded?

  • If the final equipment is louder than what was modeled, does the county get to review it again?

The cleanup bond

The developer says it will post “a bond, letter of credit, or other acceptable financial security” to cover removing the project and restoring the land (p. 10). The amount would cover “net” costs, after subtracting the expected salvage and resale value of the equipment, and would be updated before construction and periodically after (p. 37). The developer’s own cleanup estimate, Attachment 5, puts the cost of removing everything at $13.6 million and the salvage value at $22.4 million, leaving an $8.8 million surplus. By the developer’s own formula, the bond would be zero. More than half the salvage is $12.5 million from reselling 372,216 used panels, priced from a valuation that reflects panels in “almost-new condition” in their first five years. The batteries are counted as a cost, not salvage.

Cleanup would begin “if the entire Project has not operated for a period of up to three years,” or when it reaches the end of its useful life (p. 36). The cleanup plan itself mentions only the end of useful life. Equipment would be removed “including components less than 3 ft below the ground surface.” The cleanup plan uses 4 feet: underground lines deeper than that may be left in place. The application says panels and batteries can be recycled, resold or put in municipal landfills (pp. 24-25).

Questions to ask:

  • The developer’s estimate shows salvage exceeding cleanup cost by $8.8 million. Will the county require a bond for the full $13.6 million cleanup cost, and set it before approval rather than after?

  • Should salvage value be subtracted at all, when it assumes nearly new panels? Who decides what the equipment will be worth decades from now?

  • Who holds the security, and does it stay in place if the project is sold?

  • If only part of the project stops running, does any cleanup duty start? Would a shorter idle period be reasonable?

  • What would be left in the ground deeper than 3 feet?

The money figures don’t match

The application’s executive summary says the project would bring about $23 million in tax revenue and support $29 million in new local earnings across about 300 jobs (p. 10). The developer’s own economic study, Attachment 1, comes in much lower.

Figure Notice packet Developer’s economic study (Att. 1)
Local taxes over 35 years $23 million (p. 10); $13.7 million to the county plus $7.1 million to schools and special districts (p. 25) $13.93 million for all taxing districts combined, schools included
County government’s share Not stated $2.79 million, about $80,000 a year
School district $7.1 million $7.12 million, partly offset by lost state aid
Construction jobs About 300 (p. 10); 338 (p. 25) 95 in the county; 280 statewide
Local earnings $29 million (p. 10) $7.9 million in the county during construction, then about $503,000 a year

The study’s $13.93 million averages $397,989 a year across every taxing district. Payments would start at $491,485 a year and fall after year 20, when the batteries reach the end of their tax life, and again after year 30 (Att. 1, p. 31). The packet’s $13.7 million plus $7.1 million appears to count the school money twice. Empire Electric’s October release used $13.9 million; display boards at Valley Range’s Nov. 10 community meeting said $18 million in new property taxes and 103 jobs.

A planning commissioner said at the Nov. 12 meeting that the total “sounds like a big number until you divide by the 35 years.” The application also promises $5,000 a quarter to local community groups, but only during permitting and construction (p. 28).

Questions to ask:

  • Why does the application’s summary claim $23 million in taxes and about 300 jobs when the developer’s own study says $13.93 million and 95 county jobs? Which figures should the commission rely on?

  • Would the developer agree to community payments that continue after construction, written in as a condition?

Promises that aren’t conditions yet

The application describes setbacks of at least 500 feet from property lines, 1,500 feet or more from County Road H and 2,000 feet or more from U.S. 160 (p. 38), and at least 1,700 feet from the Cielo Bonito Ranchos North subdivision (p. 18). Planning staff’s notes say this project carries a 500-foot minimum setback from property lines (p. 51). The developer says no construction, operating or decommissioning traffic will use County Road H (p. 40). The site plan marks the U.S. 160 emergency access as “to be determined” (p. 57).

Where bigger setbacks weren’t possible, the developer offers some neighbors a “Good Neighbor Agreement.” If an eligible owner sells during the project’s life and an independent assessor finds the project kept the home from fair market value, the developer pays the difference (p. 18). The application gives no dollar cap. The Current reported in October, citing The Journal, that the agreements would cover up to $75,000.

Questions to ask:

  • Will the setbacks and the no-Road-H promise be written into the permit as conditions?

  • Does the 500-foot minimum apply to the battery yard as well as the panels? At an Oct. 5 workshop, commissioners asked that the county’s solar setback be written to cover battery storage too; the Current reported then that the change had not been adopted.

  • Where would the emergency access road go, and will that be settled before approval?

  • Who qualifies for a Good Neighbor Agreement, what is the cap, and would it bind a future owner? Will it be a permit condition?

Wildfire and water

The application form marks fire and wildfire protection as a standard that needs mitigation (p. 4), and so does the developer’s mitigation plan (p. 42). The county’s copy of the threshold summary, later in the packet, marks it as meeting the standard (p. 53), though the developer’s own copy (file AA03) says it requires mitigation. In the county’s copy, the Wildfire Adapted Partnership says a wildfire mitigation plan “is necessary” for the site, where most of the ground cover is sagebrush with sections of piñon-juniper. Staff notes say the developer has been told to contact the partnership.

County standard 12 requires “proof of availability and adequate flow” of water (p. 4). The application marks it as met, but says the construction water source hasn’t been chosen. The permit summary adds another option: a hookup to “a municipal water main along County Road H” (Attachment 19). The developer is talking with the Dolores Water Conservancy District and an irrigation district and will confirm a supply before construction (p. 40).

Questions to ask:

  • Has a wildfire mitigation plan been done? Will one be required before a permit?

  • Does fire protection meet the county standard, or does it need mitigation? The packet says both.

  • How much water will construction take, and from where? Should proof come before approval?

Archaeology, wildlife and federal reviews

Archaeologists from Woods Canyon Archaeological Consultants recorded 75 sites on the project lands, most of them Ancestral Puebloan, dating from about A.D. 500 to 1300. They recommended 62 as eligible for the National Register of Historic Places, and rated 48 of the eligible sites high for the potential to hold human remains (Attachments 10.0 and 10.1). In an Aug. 6 email included in the filing, Accelergen’s Matt Ryan wrote that the company would avoid sites where feasible “but we will be unable to avoid all potential sites” (Attachment 10.2). Eligible sites that can’t be avoided would be excavated under a state-approved plan (pp. 20-21).

The site also lies partly in Colorado Parks and Wildlife high-priority mule deer habitat: severe winter range, a winter concentration area and a migration corridor. How deer use the site “remains largely unknown,” the developer’s 2025 wildlife survey says (Attachment 12.3). Golden eagles may forage there, and the developer says it “will evaluate the recommendation” to do a federal eagle assessment (p. 22). The Army Corps of Engineers’ finding on streams and wetlands covers an earlier 723-acre review area; the project has grown since (p. 14).

Questions to ask:

  • How many of the 62 eligible sites, and of the 48 rated high for human remains, are inside the construction footprint? Will avoiding them be a permit condition?

  • What have the Ute Mountain Ute Tribe and Mesa Verde National Park, both listed as groups the developer has worked with (p. 10), said about the sites?

  • What will protect mule deer winter range and the migration corridor during construction?

  • Will the eagle assessment be done before a vote? Does the Corps need to review the larger footprint?

How big, how long and who owns it

The packet gives several sizes. The application form lists 880.35 total acres (p. 2). The narrative describes about 1,105 acres of private land plus about 413 acres of state trust land, with about 900 acres fenced and developed (p. 11). Elsewhere it says the developer controls about 1,638 acres (p. 38). The emergency plan says “[1,529]” acres, and the attachments give five more figures, from 791 to 1,282 acres.

The developer asks that the permit stay valid through Dec. 31, 2031, because construction depends on Tri-State finishing its own network work, and then for the life of the project until cleanup ends (p. 9). The emergency plan leaves the site owner and operator as “[Project LLC name]” and “[Site Operator Name]” (plan, p. 4). In October, a fund of Fengate Asset Management, a Canadian infrastructure investor, bought Accelergen’s portfolio of projects, including Valley Range, trade publications reported. None of the 31 files mentions Fengate. The company profile in the filing names EnCap Energy Transition Fund as Accelergen’s backer, and says the project is being developed by “East Side Energy Storage LLC” (Attachment 6).

Planning staff’s notes also leave a loose end: with four workers expected on site, staff asked whether restroom facilities will be provided (p. 53). The packet holds staff notes on each county standard but no staff recommendation. A file titled “Conditions of Approval” turns out to be the developer’s own list of six proposed commitments: a setback lease on the northeast side, a weed plan, berms or plantings on the south side, Good Neighbor Agreements, a conservation agreement and continued outreach. None addresses fire water, noise limits, the bond amount, Road H or the permit term.

Questions to ask:

  • Which acreage is the permit for?

  • Why should the permit stay valid until 2031 with nothing built? What happens if construction hasn’t started by then?

  • Who will own and operate the plant? Will permit conditions bind any future owner, and will the county be told of a sale?

  • Will staff propose conditions beyond the developer’s six, and publish a recommendation before the Dec. 3 comment deadline?

Trucks, glare and the view from Mesa Verde

The traffic study, dated Nov. 18, expects 96 workers’ vehicles and 140 delivery trucks a day at the peak of construction, 126 of them tractor-trailers, for 8 to 10 months. That is 472 vehicle trips a day through one existing private driveway off U.S. 160 near mile point 44.5. Deliveries would be scheduled outside the highway’s rush hours, and the emergency access is still “under review” (Attachment 16).

The glare study predicts low-level glare, mostly at sunrise, at nine of 27 modeled viewpoints and on U.S. 160 and County Road H if the panels rest flat overnight, as planned. If they rest at a 5- or 10-degree tilt instead, the model predicts no glare at any of them (Attachment 7). No Mesa Verde viewpoint was modeled for glare. The visual simulation from the Mesa Verde Geologic Overlook, 3.5 miles from the nearest panels, was built from a layout file named “2024-10-21”; the other three simulations used the Aug. 21, 2026 layout (Attachment 7.1).

The property-value study is dated June 24, 2025, before the redesign, and describes a 1,119-acre project. It found no harm to nearby home or farm values. It couldn’t find enough homes near large Colorado solar farms for a local comparison, so it relied on sales in nine other states. It doesn’t mention Mesa Verde, tourism or the campground (Attachment 2).

Questions to ask:

  • What hours would the 140 daily trucks run? Would nighttime deliveries be allowed?

  • Would the developer accept a 5- or 10-degree overnight rest angle as a condition, since its own study predicts no glare at those angles?

  • Will the developer simulate the view from Mesa Verde with the current layout?

  • Will the commission get a property-value study that reflects the current design, the battery yard and the tourism businesses nearby?

How to weigh in

  • The hearing: Thursday, Dec. 10, 6 p.m., commissioners’ hearing room, 109 W. Main St., Cortez (Room 250, according to the agenda the county posted). Spoken comment is allowed.

  • Written comments: Use the county’s public comment form at montezumacounty.gov/public-comment/ (the permit portal’s home page links to it as “Public Comment Link”), or email publiccomment@co.montezuma.co.us. Give the application number, HIP-04-2026, and your name and address. PDF attachments are allowed, up to four files of 4 MB each. Comments filed by Dec. 3 go into the commission’s review materials.

  • The rules: Under the procedures commissioners adopted in October, each person may file one written comment per application, and it must include a name and address. Comments are accepted from county residents and others who could be affected, and the same comment goes into the record for the county commissioners’ later hearing. Nothing new can be handed in at the hearing. A map or photo used while speaking must have been filed in advance and given an exhibit number by the planning department. Since only one comment counts, put every question in a single filing.

  • Questions: Montezuma County Planning Department, (970) 565-2801 or publiccomment@co.montezuma.co.us.

After the planning commission votes, the Board of County Commissioners holds its own hearing and makes the decision. The Colorado Independent Ethics Commission said Nov. 24 that Commissioner Kent Lindsay may not vote on the project.

Read the application

These are all 31 files Montezuma County has posted for the Valley Range application, record HIP-04-2026. Each link downloads a PDF from the county’s permit portal. Files of 10 MB or more are marked. The county’s list has no Attachment 11.

Disclosure: The author, a Montezuma County resident, filed a written request with the Planning and Zoning Commission asking the applicant and county staff to clarify these points. The request takes no position on the application.

Sources: Montezuma County public notice packet, “Valley Range Energy 12.10.2026 PN Packet,” and its 30 attachments, including Attachment 18, “Draft Emergency Response Plan,” record HIP-04-2026 on the county’s permit portal; Montezuma County Resolution 12-2026 and the county’s public comment instructions; Cortez Current reporting from Oct. 10, Oct. 18, Oct. 23, Nov. 13, Nov. 14 and Nov. 25, 2026.