Cortez council's final 2027 budget vote and a $267,800 rec center roof are up Tuesday
The $39 million budget gets its public hearing and second reading on Nov. 24. Council will also consider a contract to replace the Recreation Center's leaking flat roofs, adopting the city's stormwater master plan, and two letters asking the president for flood disaster declarations.

The Cortez City Council takes its final vote on the city’s 2027 budget on Tuesday, Nov. 24, at a regular meeting that also includes a proposed $267,799.78 contract to replace the Cortez Recreation Center’s flat roofs and the adoption of the city’s stormwater master plan.
The budget, Ordinance No. 1378, is listed as a public hearing and second reading. Council passed it unanimously on first reading on Nov. 10, as the Current reported. The work session starts at 6:30 p.m. and the regular meeting at 7:30 p.m. at City Hall, 123 Roger Smith Ave., and both are streamed on the city’s website.
The budget
Finance Director Randy Bailey’s memo in the packet says the proposed budget totals $39 million in spending and asks for $5.4 million from reserves to pay for planned capital work: $1.7 million from the General Fund, $0.7 million across the street improvement and equipment funds, $1.4 million from the Recreation Center Fund, $1.1 million from the Water Utility Fund and $0.4 million from the Airport Fund.
The memo says about $3.2 million of capital spending on the governmental side goes mainly to police vehicle replacement, facility rehabilitation, street improvements and equipment, and about $3.3 million on the utility and enterprise side goes to water system infrastructure, refuse equipment, rehabilitation of the Recreation Center’s natatorium and airport operations. It calls drawing on reserves for one-time capital work “prudent at this time” because fund balances are above six months of operating costs.
The General Fund in the attached summary totals $16,536,129 for 2027, including $1,736,408 from reserves. Staff recommend approval on second and final reading. The hearing is where residents can comment on the budget before the vote.
A new roof for the Recreation Center
Parks and Recreation Director Creighton Wright’s memo says the Recreation Center’s metal roofs have held up but its flat roof sections have leaked in “virtually every” section over the past five years. Inspections found much of the more than 20-year-old membrane has pulled away from the surface, and core samples showed the insulation saturated even on a dry day. The job covers about 14,500 square feet: tearing off the membrane and insulation, repairing the deck as needed, and installing new insulation and a fully adhered TPO membrane with new flashing and drains.
The project went out to bid twice. The first round, advertised in July, drew three bids, only one of them complete, and that one was well over budget, so all were rejected. The second round drew seven:
- Element Systems, LLC: $267,799.78
- Good Knight Roofing: $299,276
- All Weather Waterproofing: $336,830
- Up Top Roofing & Exteriors LLC: $454,740.80
- JR & CO Inc.: $473,188 (ruled invalid; no bid bond)
- Alpine PRQ Topline: $488,580
- 365 Roofing: $698,216
Bids were scored 60% on cost and 40% on quality, and Element Systems, of Wheat Ridge, scored highest overall, the memo says. It would give a 24-month workmanship warranty and a 20-year manufacturer warranty, with substantial completion in 80 days, and the center is expected to stay open during the work. The project was budgeted at $500,000 from the Recreation Enterprise Fund, so the recommended bid comes in $232,200 under that figure. Staff recommend awarding the contract and authorizing the city manager to sign it.
Stormwater master plan
Council will consider Resolution No. 21, adopting the stormwater master plan prepared by Jones & DeMille Engineering as city policy. Council members discussed the plan, and a possible stormwater fee to pay for it, at their Nov. 10 work session.
Public Works Director Casey Simpson’s memo says adopting the plan has no fiscal impact and does not authorize any project or spending; the resolution says it “shall not obligate the City to construct any specific project.” The plan’s cost table lists conceptual projects across the city, the largest of them on Ash Street ($3,234,000), Chestnut Street ($2,964,000), Empire Street ($982,000) and US 491 at Broadway ($968,000), each with a 20% contingency.
Flood disaster letters
City Manager Drew Sanders asks council to let Mayor Dennis Spruell sign two letters to the president supporting Colorado’s requests for major disaster declarations, one for the Oct. 22-25 flooding and one for the Nov. 1-2 flooding. His memo says Sen. Michael Bennet’s office told the city that FEMA is treating the two floods as separate events, which requires two declarations.
The draft letter says Cortez had 4.88 inches of rain in October, about five times normal and its wettest month in 28 years of records, and that the city’s own damage was limited. It asks for FEMA Public Assistance and the Hazard Mitigation Grant Program for the affected jurisdictions.
Other business
- Ordinance No. 1379, on first reading, would let Planning and Zoning commissioners take part in meetings by video or phone, modeled on the policy council adopted for itself in 2025. The draft caps remote participation at two members per meeting and three meetings a year per member, except in emergencies, and the chair could not take part remotely except at a fully electronic meeting. The Planning and Zoning Commission recommended it unanimously on Nov. 3. Staff propose a second reading and public hearing on Dec. 8.
- Consent agenda: the Nov. 10 minutes, the expenditure list, a special event permit for the Cortez Area Chamber of Commerce’s Business After Hours on Dec. 10 from 4 to 8 p.m. at 448 W. Main St., and the renewal of the brew pub liquor license for Main Street Brewery & Restaurant at 21 E. Main St.
- An executive session is listed “as needed.”
The 6:30 p.m. work session covers a new liquor permit option called a retail establishment permit, the process for interviewing applicants for city boards and commissions, and the city manager’s year-end review.
Comments for council can be emailed to councilcomments@cortezco.gov; the agenda says comments received by 3 p.m. on the day of the meeting are delivered to council that day. Speakers at the meeting fill out an “Intent to Speak” card.
Sources: City of Cortez, Nov. 24 regular meeting agenda and packet and work session agenda.