County puts flood damage at $16.7 million in early tally

A county emergency management briefing shown to commissioners on Monday counts $6.33 million in damage to county roads and crossings, $5.2 million to the Town of Mancos and $5 million to State Highway 184. The emergency manager said the county's share is likely to grow.

A county emergency management briefing titled Flood Damage and Recovery Outlook on the meeting room screen, with headline figures of $16.71 million in public damage across all owners, $6.33 million in county public infrastructure and 45 public damage sites, a bar chart below, and an inset of the commissioners at the dais
Image: Montezuma County meeting videoThe county's flood damage briefing on screen during Monday's workshop, with the commissioners at the dais in the inset.

The October and November floods did at least $16.7 million in damage to public roads, bridges, water systems and other infrastructure in Montezuma County, according to a preliminary county briefing shown to the Board of County Commissioners at its workshop on Monday afternoon.

The two-page briefing, from Montezuma County Emergency Management and headed “Flood Damage & Recovery Outlook,” draws on the damage reports logged in the state’s CrisisTrack system through Nov. 15. It counts 45 public damage sites. Every figure in it is labeled a preliminary estimate.

Montezuma County’s preliminary flood damage figures, from CrisisTrack data through Nov. 15: $16.71 million in public damage across all owners; $6.33 million to county public infrastructure; $5.2 million to the Town of Mancos; $5 million to Highway 184 Graphic: Cortez Current. Source: Montezuma County Emergency Management briefing, Nov. 16, 2026

Where the damage is

The county’s own share is $6.33 million, nearly all of it on county roads, bridge approaches, culverts and drainage crossings — $6.322 million of washouts, eroded approaches and damaged crossings, by the briefing’s count.

County Emergency Manager Jim Spratlen told the board that figure had already changed since the briefing was prepared. After talking with Road and Bridge, he said, the county’s damage “will probably be closer to 7.3” million once more county roads are added.

The Town of Mancos accounts for $5.2 million in the briefing. Of that, $3.185 million is for major repairs to the town’s wastewater system, $2 million is for the Cottonwood Dog Park, where the briefing lists damage to the riverbank, grounds, paths and fencing, and $17,100 is for drinking-water pumps and the raw-water intake.

Another $5 million is on State Highway 184, which the briefing lists under the Colorado Department of Transportation for bridge and roadway cracking and shoulder and riverbank erosion. Spratlen said that money goes through the federal highway system rather than through FEMA or the county.

Outside the public owners, the briefing records $164,000 in damage to ditch and irrigation works and $10,000 to a privately owned bridge, and says those sites affect farm water and access to private property “in ways not fully conveyed by dollar estimates alone.” It also counts 62 property-impact reports from residents and 52 survivor registrations.

FEMA, and the “ifs”

Spratlen said FEMA staff were in the county within about a week and a half to look at the damage, and that the county met its per-capita damage threshold. “We’re in the bucket,” he said. Whether money follows still depends on the president approving the disaster declaration Gov. Jared Polis requested, he said, and on how the state then allocates it. In past incidents he has worked, he said, reimbursement has run anywhere from 85 percent federal and 15 percent local to 75 and 25, and has taken anywhere from a year to more than three.

He urged residents with flood damage to report it online rather than by phone, saying the county does not have the staff to take all the calls. The Current has the county’s damage-reporting link and instructions.

Spratlen also told the board that county staff have put in up to 198 hours or more each over the past 14 days, and that the county’s emergency operations center has an incident support plan for the next 15 days. He said the county attorney would probably bring the board an updated resolution focused on recovery.

On water in Mancos, he said the water station at Mancos Brewing Company is still open but slowing down: the town’s residents, about 1,200 people, are off the boil order, while Mancos Rural Water’s customers, about another 1,200, have water back but are still under a boil order. Mancos Rural Water’s own notice on Monday said its order remains in effect until state officials authorize lifting it.

A request for two contract positions

Spratlen asked the board to keep paying for a public information officer and a planning section chief on contract for at least four months — he said through the end of March — to keep up with recovery paperwork and with planning for spring runoff. A commissioner asked what it would cost. County staff said both positions are now part-time, that the planning post is eight hours a week funded through the health department, and that they would come back with hourly and total costs. No figure was given and no vote was taken.

County staff also told the board they plan to open a separate flood line item in the Road and Bridge budget, in addition to the one opened in the general fund when the disaster was declared, and that the general fund can move money to Road and Bridge in a disaster and take it back when reimbursement arrives.

Road M, and the Road 39 bridge

Road and Bridge told the board that its engineer’s early figure for the two Road M washouts near Hartman Draw is almost $1.5 million, and that the cuts are 25 to 30 feet deep under a busy road carrying many utilities. Road M, Road G, Road 26 and other major collector roads north of Cortez fall under the federal highway program rather than FEMA, Road and Bridge said, so some reimbursement may come that way; Federal Highway Administration staff are due for site visits on Thursday afternoon. Whether Road M gets a like-for-like culvert or a larger concrete box culvert is still being worked out, the board was told, because a bigger opening would push more water to the crossings downstream.

Road and Bridge also said it has 15 days to tell the state what it will do about the Road 39 bridge near Mancos.

The Current reported earlier on Road M’s closure and on the county’s disaster declaration, which lets the county hire engineering help for the road without going out to bid.

At the landfill

The landfill has set up a separate code for 2026 flood loads, so it can document addresses and tonnages for the reports, and gives customers receipts they can use for FEMA claims, the board was told. The landfill has also received a waiver from the Colorado Department of Public Health and Environment allowing it to accept both friable and non-friable asbestos from flood cleanup, though it tries to send most of that to a contractor in Utah. Green waste from the floods is free at the landfill through Dec. 31.

The rest of the workshop

  • Southwest Health System. Joe Theine, who gave the hospital system’s update, told the board this is his last week at Southwest Health System, which is bringing in an interim chief executive this week while it searches for a permanent one. He said the hospital, which was just under a $2 million operating loss for the year at midyear, has made up much of that ground this fall, has been awarded more than $4 million in outside grants and gifts this year, and will present a 2027 budget to its board in mid-December that keeps today’s services and limits capital spending to repairs.
  • Grants. Faedra Grubbs told the board the county is working on about 16 grants and received a little over $721,000 in reimbursements through October. She said her replacement starts Dec. 7.
  • Albertsons opioid settlement. County Attorney Stephen Tarnowski recommended that the county join the settlement, as it has joined earlier opioid settlements, saying a county of its size is better served by joining than by bringing its own suit. Joining means giving up other legal remedies; he said he had not seen a dollar figure, and that the deadline to join is the end of the year.
  • Social media policy. No document was attached, so the chairman moved the discussion to next week.
  • Dolores law enforcement contract. The sheriff told the board the 2027 contract with the Town of Dolores is essentially unchanged from this year’s: one deputy, for $143,000 a year. The town signed it at its last board meeting.
  • Veterans claims software. Veterans Service Officer Travis Parker said an additional license for the claims software his office uses, which the state does not cover, costs $5,562 a year and is in his budget.
  • Transfer station design. The landfill’s Mel Jarmon asked to spend money on engineering for a planned recycling and transfer station building, which he said could cost $1.7 million to $1.8 million and for which the county applied for a state grant with a 30 percent county share. The state wants line-item cost estimates before it will fund it, and an engineer from Jones & DeMille Engineering estimated the design work at $90,000 to $120,000, the board heard. Commissioners said that is above the $50,000 limit for gathering quotes, so it must go out for proposals under the county’s procurement policy, and asked for the request for proposals quickly.
  • Circular Action Alliance. The county’s agreement with the Circular Action Alliance, which reimburses recycling programs for labor and equipment under the state’s producer responsibility law, is ready to sign after the state granted the waivers the county asked for.
  • Boom mower. Road and Bridge is seeking bids on a 3-point boom mower for its new tractor, which it estimated at about $40,000 to $45,000. The county’s request for proposals says bids are due Dec. 2 at noon. The county also reminded the public that surplus equipment is up for auction on Purple Wave until early December.

What happened Tuesday

The opioid settlement, the Dolores contract, the software agreement, the transfer station bid, the Circular Action Alliance agreement and the mower request were all on the consent agenda for the commissioners’ regular meeting on Tuesday morning, according to the county’s posted agenda. That meeting also included a Board of Health decision on hiring a new public health director, the county’s social media policy and 2027 employee insurance rates. The Current will report what the board decided once the recording can be reviewed.

This story was written from the county’s recording of the Nov. 16 workshop and the agenda the county posted with it. Figures given only aloud at the workshop are attributed to the person who gave them.